Blair Road Culvert and Retaining Wall Replacement at Devil’s Creek

Project Overview

The installation of one 2400 x 1500mm precast box culvert with two concrete headwalls, traffic control, excavation, dewatering, slope stabilization, rip rap placement, construction of road sub-base, base, asphalt pavement, curb and gutter as well as removal and replacement of guide rail. Removal and replacement of 0.3m x 1m tall, 12m long retaining wall in Devil’s Creek.

Owner

City of Cambridge

Engineer / Consultant

GHD